Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network.
For an organization, the following project schedule is given. Assume that all times are in days. Task Predecessor Normal Time Crash Time Crash Cost Slope (per day) A None 7 7 NA B A 3 3 NA C A 8 4 600 D A 4 4 NA E B 6 5 600 F C, D … Read more