This assignment is from a housing project in Sydney. Your task is to develop a schedule model for this project in MS Project
Requirements
• Project will start on Monday 3rd October 2022.
• Observe all public holidays as per official holidays in NSW during the project.
• Daily hours for construction workers are from 7AM to 11AM and 11:30AM to 3PM.
• Onsite work is for 6 days in a week, Sunday is a holiday.
• Last Saturday of every month is a day off (non-working time).
• Highlight critical path in a shade of red.
• Tasks should have WBS outline numbers.
• The project should use summary tasks to enable detail to be collapsed or expanded.
• Each phase must have a completion milestone.
• In the Gantt view, summary tasks and milestones must show Name to the left and Duration to the right.
• In the Gantt view, task bars (critical & non-critical) should show duration on the left and resource names to the right.
• Schedule tasks as Fixed Duration (not fixed units or fixed work).
• Each task must have at least one assigned resource with the required skill.
• When resources are overallocated adjust the units (Assign Resources in top menu) to maintain completion dates.